Strengthening Ukraine’s Power Backbone
Project: USAID Energy Security Project (UESP-2023-003, Lot 3)
Project Story
In August 2023, we commenced the supply of a 330/150/10 kV, 250 MVA autotransformer to Ukraine’s national grid operator, under the USAID Energy Security Project.
Even a single autotransformer at this scale plays a vital role in delivering stable, high-voltage electricity to key regions, industries, and communities. Our work supports Ukraine’s ongoing efforts to fortify its grid and ensure a more resilient future.
Key Facts
- Location: Ukraine
- Scope: 1 × 330/150/10 kV, 250 MVA autotransformer
- Client: National Grid Operator (via USAID ESP)
- Terms: Delivered and unloaded on-site
- Commencement: August 2023
Our Commitment
Through every phase — from production to delivery — we delivered precision engineering, quality you can trust, and full compliance with international standards. This project marks another step forward in our mission to power a stronger, more energy-secure Ukraine.